The Columbia Generating Station, the Northwest’s only commercial nuclear power plant, is again supplying enough electricity to power about 1 million homes after a 65-day refueling outage.

It reconnected to the power grid at about 5 p.m. Monday.

The outage, originally planned for 56 days, was extended for nine more days, as a variety of planned tasks took longer than expected.

Some of the 2,000 additional workers hired for the outage replaced 256 of the 764 nuclear fuel assemblies in the reactor core with new fuel. Every two years, a third of the reactor’s fuel is replaced. After used fuel is cooled, it is stored on a secure outdoor pad near the reactor until the nation has a permanent repository for used reactor fuel.

Energy Northwest, which operates the reactor, also took advantage of the reactor shutdown to complete thousands of other maintenance tasks and projects, some of which could only be done when the reactor was not operating.

Energy Northwest’s Columbia Generating Station near Richland is the Northwest’s only commercial nuclear power plant. The contrast of the dark sky and morning light coming up behind the water vapor clouds from the reactor’s cooling towers caught the eye of Judi Hastings, who captured this photo at 4:20 a.m. on a day it was at full operation.
Energy Northwest’s Columbia Generating Station near Richland is the Northwest’s only commercial nuclear power plant. The contrast of the dark sky and morning light coming up behind the water vapor clouds from the reactor’s cooling towers caught the eye of Judi Hastings, who captured this photo at 4:20 a.m. on a day it was at full operation. Courtesy Judi Hastings

“The work accomplished during this outage enhances Columbia’s reliability and strengthens our mission to provide carbon-free, cost-effective energy,” said Energy Northwest CEO Bob Schuetz. “The team completed an impressive amount of work, and we’re pleased to once again be producing much-needed electricity for the region.”

A longer than usual outage was planned this spring and more workers were hired after a major project was planned — installing a new adjustable speed drive system. The system needed to be replaced after there were a few issues that required powering down to fix components.

The speed drive controls the pumps that control the water inside the core, which in turn controls the amount of power the reactor produces, according to Energy Northwest.

The heat produced by a chain reaction boils the water within the core, creating steam that turns turbines attached to an electric generator.

The Columbia Generating Station near Richland, Wash., reconnected to the Northwest power grid June 16 after a refueling outage. The photo was taken at the start of the 65-day outage.
The Columbia Generating Station near Richland, Wash., reconnected to the Northwest power grid June 16 after a refueling outage. The photo was taken at the start of the 65-day outage. Energy Northwest

Other work included repairing the circulating water basin, electrical generator inspection and replacing a reactor recirculation pump and motor.

The spring refueling outages are timed to match the spring snow melt and runoff in the Northwest, when hydroelectric generation is high and the impact of a temporary halt to nuclear power production is minimized.

The Columbia Generating Station, about 10 miles north of Richland, is the third largest electricity generator in Washington state. The electricity it generates is sold at cost to the Bonneville Power Administration for distribution.

The Columbia Generating Station near Richland, Wash., reconnected to the Northwest power grid June 16 after a refueling outage. The photo was taken at the start of the 65-day outage.
The Columbia Generating Station near Richland, Wash., reconnected to the Northwest power grid June 16 after a refueling outage. The photo was taken at the start of the 65-day outage. Energy Northwest

This story was originally published June 17, 2025 at 11:27 AM with the headline "Nuclear power plant near Richland refueled, again supplying power to the Northwest."

AC
Annette Cary
Tri-City Herald
Senior staff writer Annette Cary covers Hanford, energy, the environment, science and health for the Tri-City Herald. She’s been a news reporter for more than 30 years in the Pacific Northwest. Support my work with a digital subscription
Get unlimited digital access
#ReadLocal

Try 1 month for $1

CLAIM OFFER