Agency reports progress on collapsed Skagit River bridge

ASSOCIATED PRESSMay 29, 2013 

— Crews are making progress at the collapsed Interstate 5 bridge on the Skagit River that has detoured traffic on the main route between Seattle and Vancouver, British Columbia, the Washington Transportation Department reported Wednesday.

About three-fourths of the wreckage that fell into the water last Thursday has been removed, agency spokesman Bart Treece said.

"We've got a good chunk of all the debris removed. That was the easy stuff for these hydraulic shears," Treece said. "But the bridge deck is tough. It's a matter of breaking it up and removing."

Some places have to be kept intact for the National Transportation Safety Board investigation. Divers are being used.

The next step will be an inspection of the bridge piers for damage. After that, the department will have a better idea whether it can meet the governor's challenge to install a temporary bridge by mid-June.

Two of 10 truckloads of temporary bridge parts have arrived at Mount Vernon, from Washougal, Wash., and New Jersey, Treece said.

The bridge collapsed after a semi-truck with an oversize load clipped a steel truss on the span, sending a car and pickup truck with a trailer into the river. A couple in the pickup and a man in the car escaped their wrecked vehicles and the frigid water with minor injuries.

The bridge carried 71,000 vehicles a day. Now, traffic is backing up a mile or two on the interstate as cars and trucks make their way on alternate routes through Mount Vernon on the south side and Burlington on north side of the river.

"People have to figure out what works for them," Treece said. "It takes time for people to figure out what the new normal is."

Mount Vernon is about 40 miles south of the Canadian border and the I-5 crossing is the third-largest border crossing with Canada. The problem at the Skagit River bridge is a major concern for trade and tourism in both directions, officials have said.

The temporary bridge being assembled by New Jersey-based Acro Bridge will be 160 feet long with two sections, each 24 feet wide. Treece described it as an "industry size erector set." That will be enough for two lanes in each direction. It will be a little narrower than the bridge it replaced, so the speed limit will be lowered from 60 mph.

A longer-range bridge replacement will depend on several factors, including the NTSB investigation, Treece said.

Bellingham Herald is pleased to provide this opportunity to share information, experiences and observations about what's in the news. Some of the comments may be reprinted elsewhere in the site or in the newspaper. We encourage lively, open debate on the issues of the day, and ask that you refrain from profanity, hate speech, personal comments and remarks that are off point. Thank you for taking the time to offer your thoughts.